Retrofitting Non-LED Lighting to LED Lighting in Educational Buildings

Business Needs/Problem Statement

The educational building, constructed in the 2000s, currently utilizes traditional fluorescent lighting fixtures across its classrooms, science labs, corridors, and common areas.

Project Overview

Type

Educational building

Size

150,000 sq. ft

Previous Construction Year

Early 2000s

Location

Downtown, Chicago, Illinois, USA

Inputs from Client & Primary objectives

The feedback from Architectural & Lighting Consultants

Applicable Codes and Standards

Local Authority Requirements

Challenges Faced

Our Solutions /Approach

LED Fixture Selection

Installation and Commissioning

Lighting Design Optimization

Advanced Lighting Controls

Performance Testing

Training and Documentation

Before - Existing lighting fixture to be removed is from the Lithonia 2VT8 series.

After- New lighting fixture installed is from Lithonia 2BTL4 series.

Executive Steps by Edifice Expert

Site Assessment and Analysis

Installation and Integration

Design Development

Procurement and Logistics

Testing and Validation

Occupant Feedback and Fine-Tuning

Benefits of Our Upgraded LED Lighting System

Impact/Result

The successful retrofitting of the educational building’s lighting system with LED technology took 9 months and encompassed the planning, procurement, installation, and commissioning phases. It exemplifies a commitment to energy efficiency, sustainability, and occupant well-being.

By leveraging expertise from architectural and lighting consultants and partnering with reputable manufacturers like Acuity Brands, the client achieved significant improvements in lighting performance, operational efficiency, and environmental stewardship. An estimated annual energy savings of 50%, with a projected payback period of 3.5 years based on reduced utility costs and maintenance savings.

Additionally, an improved lighting environment supported student learning outcomes, comfort, and overall educational experience within the building.

This case study underscores the importance of strategic planning, technical expertise, and collaboration in implementing impactful building upgrades that enhance economic savings and environmental sustainability.

Before: Sample drawing

After - Sample drawing